The Contractor, Bobby Luttrell and Sons, continues to work on this project as weather permits.  Below is the anticipated schedule of the project with completion of the project anticipated in May 2019.  Weather and groundwater issues may factor in on the delay of the project.

Install 8” force main across runway – Current – January 25

Install 6” force main from Roman Meadow to Fischer Road – complete by January 31

Install 6” force main from Fischer Road to Keller Road –  completed by February 15

Install 6” force main from under Gerald Drive (Friendly Park) January 28 – February 22

Install 6” force main under Panther Creek January 28- February 22

Install Green Acres Pump Station – April

Install Friendly Park Pump Station – April

Completion in May 2109

 

If you have any questions relating to this project, please call (270) 687-8440.